Unit Dimensions & Safety Clearances
Generator Set Footprint (including SCR)
ft
ft
Safety Clearance Requirements
ft / end
Added to both ends of the unit along its length.
ft / side
Added to both sides of the unit along its width.
⚡
Power & Redundancy Requirements
MW
MW
units
N+1 = enter 1. N+2 = enter 2. Add to minimum required count.
📊
Results Summary
Min Units Required
—
units (rounded up)
Total Units (N+)
—
units including spares
—
Per-Unit Envelope
—
sq ft / unit
—
Total Site Footprint
—
sq ft
Total Site Area
—
acres
🔲
Unit Envelope Diagram
📋
Calculation Breakdown
| Parameter | Value | Notes |
|---|---|---|
| Unit footprint | — | Length × Width (bare unit) |
| Clearance envelope | — | (L + 2×end) × (W + 2×side) |
| Envelope dimensions | — | Total length × total width per unit |
| Min units (MW math) | — | Total MW ÷ MW per unit, rounded up (ceiling) |
| N+ spares added | — | User-defined backup / redundancy units |
| Total units | — | Min required + N+ spares |
| Total installed MW capacity | — | Total units × MW per unit |
| Total square footage | — | Total units × unit envelope sq ft |
| Total acres | — | Total sq ft ÷ 43,560 |